Release process

oVirt Release Process

General

  1. oVirt will issue a new release every 6 months.
    • EXCEPTION: First three releases will be issued in a ~3 month interval.
    • Exact dates must be set for each release.
  2. A week after the n-1 release is out, a release criteria for the new release should be discussed.
    • Release criteria will include MUST items and SHOULD items (held in wiki)
      • MUST items will DELAY the release in any case.
      • SHOULD items will include less critical flows and new features.
      • SHOULD items will be handled as "best-effort" by component owners
    • Component owners (e.g. Node, engine-core, vdsm) must ACK the criteria suggested.
    • Release criteria discussions shouldn't take more then 2 weeks
    • Progress on MUST items should be review every month, during the weekly meeting
  3. Discuses the new version number according to the release criteria/amount of features.
    • Versions will be handled by each component.
    • The general oVirt version will the engine version.
  4. 60 Days before release - Feature freeze
    • EXCEPTION: 30 days for 3 month release cycle
    • All component owners must create a new versioned branch
    • "Beta" version should be supplied immediately after.
      • And on a nightly basis afterwards.
    • Stabilization efforts should start on the new builds.
    • Cherry-pick fixes for high priority bugs.
      • Zero/Minimal changes to user interface.
      • Inform in advance on any user interface change, and any API change.
    • At this stage, we should start working on the release notes.
  5. 45 days before release - Test Day
  6. 30 days before release - release candidate
    • EXCEPTION: 15 days for 3 month release cycle
    • If no blockers (MUST violations) are found the last release candidate automatically becomes the final release.
      • Rebuild without the "RC" string.
      • ANOTHER OPTION- Avoid "Beta" or "RC" strings, just use major.minor.micro, and bump the micro every time needed.
    • Release manager will create a wiki with list of release blockers
    • Only release blockers should be fixed in this stage.
    • OPTIONAL: final release requires three +1 from community members
      • This item is currently optional, I'm not sure what a +1 means (does a +1 means "I tested this release", or "This release generally looks fine for me"?)
  7. Create a new RC if needed
    • There must be at least one week between the last release candidate and the final release
    • Go/No go meetings will happen once a week in this stage.
      • Increase the amount of meeting according to the release manager decision.
      • Release manager will inform the community on any delay.
    • Official vote as described in http://www.ovirt.org/governance/voting/
  8. Release
    • Create ANNOUNCE message few days before actual release.
    • Move all release candidate sources/binaries into the "stable" directory
    • Encourage community members to blog / tweet about the release
    • PARTY